Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, August 10, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Walkway Canopy at
B.T. Washington Elementary School

EXECUTIVE SUMMARY

Harvard Jolly, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 5, 2009, the Board awarded the contract for construction to the low bidder, D.B. Construction Services, Inc. The scope of work provided for a walkway canopy at B.T. Washington Elementary School.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

Hillsborough County agreed to reimburse the District for construction of the project; therefore, there was no financial impact to the District.

Contract Status:
Contract Sum: $96,603.00
Approved Change Orders: $2,290.00 Credit (See Attachment)
Revised Contract Sum: $94,313.00
Payments to Date: $86,942.70
Balance Due: $7,370.30
Revised Construction Cost: $94,313.00

Required Substantial Completion Date: August 19, 2009
Approved Time Extension: 32 Calendar Days (See Attachment)
Revised Required Substantial Completion Date: September 20, 2009
Substantial Completion Date: September 18, 2009

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.06d.
Hillsborough County Public Schools (Florida) * Mtg.#20100810_417 * Section A Item# 6.06d.