Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, October 26, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Heating, Ventilating, and Air Conditioning (HVAC) Renovation at
Summerfield Elementary School

EXECUTIVE SUMMARY

On November 18, 2008, the Board appointed Forney Engineering, Inc. to provide design services. On May 19, 2009, the contract for construction was awarded to the low bidder, Air Mechanical & Service Corp. The scope of work provided for a complete renovation of the HVAC system at Summerfield Elementary School. The scope also included replacement of existing lighting with new energy efficient lighting.

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction Funds.

Contract Status:
Contract Sum: $1,447,725.00
Approved Change Order: $66,393.05 Credit (See Attachment)
Revised Contract Sum: $1,381,331.95
Payments to Date: $1,245,598.33
Balance Due: $135,733.62
Revised Construction Cost: $1,381,331.95

Required Substantial Completion Date: August 23, 2009
Substantial Completion Date: August 10, 2009

EVALUATION

SUBMITTED BY: Ellis Curry, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.05k
Hillsborough County Public Schools (Florida) * Mtg.#20101026_429 * Section A Item# 6.05k