Facilities Action Item |
DATE: Tuesday, October 2, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of The Architectural Practice, Inc. On May 16, 2006, the Board awarded the contract for construction management services to Ellis Construction Company, Inc. The scope of work provides for a new 720 student station elementary school.
This change order provides for final reconciliation of the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2004C ($10,000.00) and Classrooms for Kids 2005 ($911,792.00).
Contract Status:
Contract Sum: $10,911,792.00
Change Orders Previously Approved: $2,839,611.45 Credit
Change Order Recommended Herein: $5,569.30 Extra
Revised Contract Sum: $8,077,749.85
Revised Construction Cost: $11,054,600.88
Contract Completion Date: May 10, 2007
EVALUATION
SUBMITTED BY: Eugene Runnels, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.08 | |
Hillsborough County Public Schools (Florida) * Mtg.#20071002_267 * Section A Item# 6.08 |