Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, October 2, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Construction Documents and Guaranteed Maximum Price for Classrooms for Kids Addition at
Wharton High School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed Holmes Hepner and Associates Architects and J.O. DeLotto and Sons, Inc. to provide design and construction management services. This addition is necessary to meet class size reduction requirements. The scope of work provides for the addition of 16 classrooms.

Approval of the guaranteed price will provide a maximum cost for the facility. Project completion is scheduled for August 4, 2008.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $2,186,175. The construction budget is $2,463,000. This item is included in the District Capital Outlay: Classrooms for Kids.

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.05d
Hillsborough County Public Schools (Florida) * Mtg.#20071002_267 * Section A Item# 6.05d