Approve Change Order No. 1 in the Amount of $19,284.85 Extra and Change Order No. 2 in the Credit Amount of $126,487.86 for Roofing and HVAC Replacement at
Chamberlain High School

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Tagliarini Architectural Group, PA. On May 29, 2007, the Board awarded the contract to the low bidder, Cason Construction Management, Inc. The scope of work includes a new roof over the Gym and Cafeteria and replacement of the heating, ventilating, and air conditioning (HVAC) system.

Change Order No. 1 provides for mechanical and electrical modifications that were beyond the scope of the original contract. Change Order No. 2 provides for final reconciliation of the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance ($809,792) and 2 Mill ($320,000).

Contract Status:
Contract Sum: $1,129,792.00
Change Order No. 1 Recommended Herein: $19,284.85 Extra
Change Order No. 2 Recommended Herein: $126,487.86 Credit
Revised Contract Sum: $1,022,588.99
Revised Construction Cost: $1,141,869.99

Contract Completion Date: August 17, 2007

EVALUATION

SUBMITTED BY: Ernie MacFerran, Mechanical Engineer

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.10
Hillsborough County Public Schools (Florida) * Mtg.#20071106_269 * Section A Item# 6.10