Facilities Action Item |
DATE: Tuesday, November 20, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the engineering firm of ASR Engineering, Inc. On November 21, 2006, the Board awarded the contract to the low bidder, Davey and Associates. The scope of work provided for replacement of the chiller.
The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract document and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item was included in the District Capital Outlay: 2 Mill.
Contract Status:
Contract Sum: $74,900.00
Change Order Previously Approved: $2,227.00 Credit
Revised Contract Sum: $72,673.00
Payments to Date: $67,410.00
Balance Due: $5,263.00
Revised Construction Cost: $72,673.00
Contract Completion Date: January 2, 2007
Substantial Completion Date: December 28, 2006
EVALUATION
SUBMITTED BY: Ernie MacFerran, Mechanical Engineer
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.31a | |
Hillsborough County Public Schools (Florida) * Mtg.#20071120_270 * Section A Item# 6.31a |