Facilities Action Item |
DATE: Tuesday, November 20, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Reliable Group Architects. On May 8, 2007, the Board awarded the contract to the low bidder, Cason Construction Management, Inc. The scope of work provides for heating, ventilating, and air conditioning (HVAC) equipment, canopy repair, and painting.
This change order provides for additional construction work required as a result of unforeseen conditions.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.
Contract Status:
Contract Sum: $682,622.00
Change Order Recommended Herein: $70,517.00 Extra
Revised Contract Sum: $753,139.00
Revised Construction Cost: $753,139.00
Contract Completion Date: October 1, 2007
EVALUATION
SUBMITTED BY: Ernie MacFerran, Mechanical Engineer
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.20 | |
Hillsborough County Public Schools (Florida) * Mtg.#20071120_270 * Section A Item# 6.20 |