EXECUTIVE SUMMARY
Suncoast Architectural Studios, Inc. and Kenyon and Partners, Inc. were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provides for resurfacing of existing pavement at King High School. Additional scope includes new lighting for the student parking lot.
This change order provides for replacement of existing through-walk drain, painting of existing wheel stops and ends of new traffic separators, and asphalt overlay of existing Driver's Ed range.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: 2 Mill.
Contract Status:
Guaranteed Maximum Price: $546,123.96
Change Order Recommended Herein: $73,561.84 Extra
Revised Guaranteed Maximum Price: $619,685.80
Revised Construction Cost: $619,685.80
Contract Completion Date: August 16, 2007
EVALUATION
SUBMITTED BY: James Lipsey, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.16 | |
Hillsborough County Public Schools (Florida) * Mtg.#20071120_270 * Section A Item# 6.16 |