Facilities Action Item |
DATE: Tuesday, November 20, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
Suncoast Architectural Studios, Inc. and Kenyon & Partners, Inc. were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provides for resurfacing of existing pavement at Cannella Elementary School. Additional scope includes 14 new staff parking spaces and relocation of the bus loop.
This change order provides chain link fence gates for the bus loop.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: 2 Mill.
Contract Status:
Guaranteed Maximum Price: $399,259.23
Change Order Recommended Herein: $4,197.96 Extra
Revised Guaranteed Maximum Price: $403,457.19
Revised Construction Cost: $403,457.19
Contract Completion Date: August 16, 2007
EVALUATION
SUBMITTED BY: James Lipsey, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.13 | |
Hillsborough County Public Schools (Florida) * Mtg.#20071120_270 * Section A Item# 6.13 |