Facilities Action Item |
DATE: Tuesday, November 20, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On November 9, 2006, the Board appointed Holmes Hepner and Associates Architects and The Morganti Group, Inc. to provide design and construction management services. The scope of work provides for
10 new classrooms. This addition is necessary to meet class size reduction requirements. Project completion is scheduled for August 4, 2008.
Approval of the guaranteed maximum price will establish the cost for the facility.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction cost is warranted at $1,523,590. The construction budget is $1,540,000. This item is included in the District Capital Outlay: Classrooms for Kids.
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.11g | |
Hillsborough County Public Schools (Florida) * Mtg.#20071120_270 * Section A Item# 6.11g |