Facilities Action Item |
DATE: Tuesday, January 15, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On November 9, 2006, the Board appointed Harvard Jolly, Inc. and Greater Bay Construction Co., Inc. to provide design and construction management services. This addition was necessary to meet class size reduction requirements. The scope of work provides for the addition of 12 classrooms.
This change order provides a credit for the direct purchase of materials, in accordance with the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Classrooms for Kids.
Contract Status:
Guaranteed Maximum Price: $2,077,794.00
Change Order Recommended Herein: $317,759.44 Credit
Revised Guaranteed Maximum Price: $1,760,034.56
Revised Construction Cost: $2,059,241.57
Contract Completion Date: August 4, 2008
EVALUATION
SUBMITTED BY: Jill Edwards, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.09 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080115_285 * Section A Item# 6.09 |