Facilities Action Item |
DATE: Tuesday, January 15, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Change Order No. 2 in the Credit Amount of $156,970.36 for Renovation at
Cork Elementary School
EXECUTIVE SUMMARY
This project was planned by the architectural firm of John J. McKenna Architect P.A. On January 16, 2007, the Board appointed the construction management firm of Vogel Bros. Building Co. The renovation of existing facilities includes new roofing, air conditioning equipment and ductwork, upgraded low voltage and electrical systems, flooring, canopy for Building 1, handicap accessibility modifications, and reconfiguration of existing bus and parent driveways.
This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Community Investment Tax.
Contract Status:
Guaranteed Maximum Price: $4,250,498.00
Change Order Previously Approved: $650,344.72 Credit
Change Order Recommended Herein: $156,970.36 Credit
Revised Guaranteed Maximum Price: $3,443,182.92
Revised Construction Cost: $4,204,046.21
Contract Completion Date: December 11, 2007
EVALUATION
SUBMITTED BY: Jill Edwards, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.08 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080115_285 * Section A Item# 6.08 |