SUBJECT / RECOMMENDATIONS

Approve Change Order No. 3 in the Amount of $14,577.05 Net Extra for Renovation at
Knights Elementary School

EXECUTIVE SUMMARY

On July 11, 2006, the Board appointed Reynolds, Smith and Hills, Inc. and Mathews Construction to provide design and construction management services. The renovation of existing facilities provides for a new walkway canopy and fire sprinkler system; reconfiguration of driveways and visitor parking; interior and exterior painting; and replacement of roof, plumbing fixtures, exterior doors, low voltage systems, and heating, ventilating, and air conditioning (HVAC) equipment.

This change order provides for the attachment of existing rooftop mechanical equipment to the building, to meet code requirements. A credit is included for work deleted from the scope.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Capital Outlay and Debt Service (CO and DS) 06A ($3,000,000) and Community Investment Tax (CIT) 06 ($450,000).

Contract Status:
Guaranteed Maximum Price: $3,450,000.00
Change Orders Previously Approved: $53,138.96 Extra
Change Order Recommended Herein: $15,449.25 Extra and $872.20 Credit
Revised Guaranteed Maximum Price: $3,517,716.01
Revised Construction Cost: $3,517,716.01

Contract Completion Date: July 14, 2008

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.07