Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, April 15, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 4 in the Amount of $1,886.00 Extra for HVAC, Canopy, and Painting Renovations at
Progress Village Middle School

EXECUTIVE SUMMARY

Reliable Group Architects was selected from the approved Continuing Services Consultants list to provide architectural services. On May 8, 2007, the Board awarded the contract to the low bidder, Cason Construction Management, Inc. The scope of work provides for heating, ventilating, and air conditioning (HVAC) equipment, canopy repair, and painting.

This change order provides for modifications to ductwork and air intakes to address unforeseen conditions.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.

Contract Status:
Contract Sum: $682,622.00 Extra
Change Orders Previously Approved: $70,940.48 Extra
Change Order Recommended Herein: $1,886.00 Extra
Revised Contract Sum: $755,448.48
Revised Construction Cost: $780,490.48

Contract Completion Date: October 1, 2007

EVALUATION

SUBMITTED BY: Ernie MacFerran, Mechanical Engineer

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.29
Hillsborough County Public Schools (Florida) * Mtg.#20080415_291 * Section A Item# 6.29