Approve Change Order No. 2 in the Amount of $8,859.03 Extra and Change Order No. 3 in the Credit Amount of $232,291.62 for Renovation at
Lake Magdalene Elementary School

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Abell Garcia Architects, P.A. This renovation of existing facilities includes new roofing, air conditioning, electrical and communication systems, fencing, painting, handicap accessibility modifications, and canopy repairs. On January 16, 2007, the Board appointed the construction management firm of Greater Bay Construction Co., Inc. to provide construction management services for the project, and has previously approved their guaranteed maximum price and subsequent change orders.

Change Order No. 2 provides for final reconciliation of the Direct Purchase Program. Change Order No. 3 provides credits for project savings and the return of unused contingency funds.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax.

Contract Status:
Guaranteed Maximum Price: $3,745,127.00
Change Order Previously Approved: $585,531.06 Credit
Change Order No. 2 Recommended Herein: $8,859.03 Extra
Change Order No. 3 Recommended Herein: $232,291.62 Credit
Revised Guaranteed Maximum Price: $2,936,163.35
Revised Construction Cost: $3,479,674.70

Contract Completion Date: December 11, 2007

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Maintenance
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004