Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 20, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 6 in the Credit Amount of $8,028.00 and Acceptance of Project for
Chiles Elementary School, Classrooms for Kids Package 5

EXECUTIVE SUMMARY

On September 7, 2004, the Board appointed Atelier AEC, Inc. and Christiano Construction Company, Inc. to provide design and construction management services for classroom additions at Brooker, Temple Terrace, and Yates Elementary Schools, and Burns Middle School. On March 14, 2005, additions at Tampa Palms and Chiles Elementary Schools were added to the package. The scope of work provided for the following additions: 18 classrooms at Brooker, 8 classrooms at Chiles, 12 classrooms at Tampa Palms, 14 classrooms at Temple Terrace, 12 classrooms at Yates, and 12 classrooms plus group toilets at Burns. These additions were necessary to meet class size reduction requirements.

The Board approved the Guaranteed Maximum Price (GMP) for the entire package on July 12, 2005. After Board approval of the GMP, the scope of work at Chiles Elementary School was changed to 16 classrooms. When the size of the Chiles addition was increased to 16 classrooms, Chiles was removed from the scope covered by the GMP for the package. The Board subsequently approved a separate GMP for the 16 classroom addition at Chiles on July 12, 2005.

This change order provides a credit for the return of unused contingency funds for the addition at Chiles. The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction ($776,922) and Classrooms for Kids ($1,827,428).

Contract Status:
Guaranteed Maximum Price: $2,604,350.00
Change Orders Previously Approved: $609,875.94 Credit
Change Order Recommended Herein: $8,028.00 Credit
Revised Guaranteed Maximum Price: 1,986,446.06
Payments to Date: $1,971,346.50
Balance Due: $15,099.56
Revised Construction Cost: $2,597,856.21

Contract Completion Date: March 19, 2007
Substantial Completion Date: May 31, 2007

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.01c
Hillsborough County Public Schools (Florida) * Mtg.#20080520_293 * Section A Item# 6.01c