Facilities Action Item |
DATE: Tuesday, June 10, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On July 26, 2005, the Board appointed Sylla, Inc. and HCBeck, Ltd. to provide design and construction management services. This new facility is a reuse of the Middleton High School design. As of the current boundaries, relief will be provided for Alonso, Gaither, and Sickles High Schools.
This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2004C ($8,054,496) and 2006 ($39,035,771).
Contract Status:
Guaranteed Maximum Price: $47,090,267.00
Change Order Previously Approved: $4,463,273.85 Credit
Change Order Recommended Herein: $498,689.67 Credit
Revised Guaranteed Maximum Price: $42,128,303.48
Revised Construction Cost: $46,808,174.72
Contract Completion Date: July 30, 2009
EVALUATION
SUBMITTED BY: John Williams, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.10 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080610_330 * Section A Item# 6.10 |