Approve Acceptance of Project for HVAC Replacement at
Limona Elementary School

EXECUTIVE SUMMARY

Lyle Engineering Group, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On February 7, 2006, the Board awarded the contract to the low bidder, Air Mechanical & Service Corp. The scope of work included replacement of the heating, ventilating, and air conditioning (HVAC) system.

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: 2 Mill.

Contract Status:
Contract Sum: $1,135,000.00
Change Orders Previously Approved: $256,126.52 Credit
Revised Contract Sum: $878,873.48
Payments to Date: $821,198.98
Balance Due: $57,674.50
Revised Construction Cost: $1,160,873.48

Original Completion Date: August 1, 2006
Time Extension Previously Approved: 90 Calendar Days
Revised Completion Date: October 30, 2006
Substantial Completion Date: October 30, 2006

EVALUATION

SUBMITTED BY: Ernie MacFerran, Mechanical Engineer

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.17d