EXECUTIVE SUMMARY
This project was planned by the architectural firm of Fleischman Garcia Architects. On January 13, 2004, the Board appointed the construction management firm of Kalemeris Construction, Inc. The scope of work included the addition of 10 primary classrooms which were added to meet class size reduction requirements.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.