Facilities Action Item |
DATE: Tuesday, July 15, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On November 9, 2006, the Board appointed Ranon & Partners, Inc. Architects and Ellis Construction Company, Inc. to provide design and construction management services. The scope of work includes the addition of 16 classrooms required for class size reduction. The field house addition will include boys and girls locker rooms, showers and toilets, office and planning area. The field house is funded by private donations and matching funds from the District.
Change Order No. 3 provides for construction of a new storage building. Change Order No. 4 provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Classrooms for Kids 2006 ($2,463,713), Community Investment Tax ($1,482,263), Community Sources (Private donations $550,000), and 2 Mill (Matching funds $50,000).
Contract Status:
Guaranteed Maximum Price: $4,595,976.00
Change Orders Previously Approved: $999,176.77 Credit
Change Order No. 3 Recommended Herein: $48,980.00 Extra
Change Order No. 4 Recommended Herein: $176,090.00 Credit
Revised Guaranteed Maximum Price: $3,469,689.23
Revised Construction Cost: $4,614,354.15
Contract Completion Date: July 21, 2008
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.17 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080715_295 * Section A Item# 6.17 |