This project was planned by the architectural firm of Rowe Architects, Inc. On June 7, 2005, the Board appointed the construction management firm of Mathews Construction. This new facility was occupied in August 2006 and relieved overcrowding at Summerfield and Collins Elementary Schools.
This change order provides credits for project savings and the return of unused contingency funds. It also provides for additional exterior painting.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 04C ($2,923,000), Classrooms for Kids ($2,166,994), and School Infrastructure Thrift Award ($5,629,622).
Contract Status:
Guaranteed Maximum Price: $10,719,616.00
Change Orders Previously Approved: $1,855,342.10 Credit
Change Order Recommended Herein: $28,068.60 Credit and $2,600.00 Extra
Revised Guaranteed Maximum Price: $8,838,805.30
Revised Construction Cost: $11,403,217.11
Original Completion Date: January 9, 2007
Time Extensions Previously Approved: 135 Calendar Days
Revised Completion Date: May 24, 2007
EVALUATION
SUBMITTED BY: Eugene Runnels, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.15 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080715_295 * Section A Item# 6.15 |