Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, July 15, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 7 in the Net Credit Amount of $25,468.60 for
Summerfield Crossings Elementary School, New Facility

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Rowe Architects, Inc. On June 7, 2005, the Board appointed the construction management firm of Mathews Construction. This new facility was occupied in August 2006 and relieved overcrowding at Summerfield and Collins Elementary Schools.

This change order provides credits for project savings and the return of unused contingency funds. It also provides for additional exterior painting.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 04C ($2,923,000), Classrooms for Kids ($2,166,994), and School Infrastructure Thrift Award ($5,629,622).

Contract Status:
Guaranteed Maximum Price: $10,719,616.00
Change Orders Previously Approved: $1,855,342.10 Credit
Change Order Recommended Herein: $28,068.60 Credit and $2,600.00 Extra
Revised Guaranteed Maximum Price: $8,838,805.30
Revised Construction Cost: $11,403,217.11

Original Completion Date: January 9, 2007
Time Extensions Previously Approved: 135 Calendar Days
Revised Completion Date: May 24, 2007

EVALUATION

SUBMITTED BY: Eugene Runnels, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.15
Hillsborough County Public Schools (Florida) * Mtg.#20080715_295 * Section A Item# 6.15