Facilities Action Item |
DATE: Tuesday, July 15, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Wilder Architecture, Inc. On January 16, 2007, the Board appointed the construction management firm of Horus Construction Services, Inc. The scope of renovation included new instructional aids and finishes; modifications to air conditioning, communication, power, and lighting systems; site grading and drainage improvements; and demolition of the original 1940's structure which included the classrooms, cafeteria, and kitchen.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Eugene Runnels, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.27d | |
Hillsborough County Public Schools (Florida) * Mtg.#20080715_295 * Section A Item# 6.27d |