Facilities Action Item |
DATE: Tuesday, August 19, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
Gottfried, Garcia and Rodriguez, Architects, AIA, PA were selected from the approved Continuing Services Consultants list to provide design services. On May 29, 2007, the Board awarded the contract to the low bidder, Quality Roofing of Florida, Inc. The scope of work provides for replacement of mechanical system components, including the condensing units and air handlers.
This change order provides for unforeseen requirements to seal corridor fire walls and replace three electrical junction boxes with larger boxes to properly enclose the wire connections. A credit is included for overtime.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) ($299,000) and 2 Mill ($100,000).
Contract Status:
Guaranteed Maximum Price: $399,000.00
Change Order Recommended Herein: $18,613.43 Extra and $219.56 Credit
Revised Guaranteed Maximum Price: $417,393.87
Revised Construction Cost: $417,393.87
Contract Completion Date: August 17, 2007
EVALUATION
SUBMITTED BY: Ernie MacFerran, Mechanical Engineer
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.15 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080819_298 * Section A Item# 6.15 |