Facilities Action Item |
DATE: Thursday, September 4, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
Long & Associates Architects/Engineers, Inc. and Halfacre Construction Company were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provides for a new lift station at North Tampa Alternative School. Project completion is scheduled for October 5, 2008.
Approval of the guaranteed maximum price will establish a cost for the project.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction cost is warranted at $49,915.50. The construction budget is $49,920. This item is included in the District Capital Outlay: Millage Funds.
EVALUATION
SUBMITTED BY: Ken Tomberlin, Relocatable Facilities Manager
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.01d | |
Hillsborough County Public Schools (Florida) * Mtg.#20080904_299 * Section A Item# 6.01d |