Facilities Action Item |
DATE: Thursday, September 4, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
Long & Associates Architects/Engineers, Inc. and Halfacre Construction Company were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provides for the interior build out of office spaces at North Tampa Alternative School. Project completion is scheduled for October 5, 2008.
Approval of the guaranteed maximum price will establish a cost for the project.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction cost is warranted at $34,635.90. The construction budget is $34,650.00. This item is included in the District Capital Outlay: Millage Funds.
EVALUATION
SUBMITTED BY: Ken Tomberlin, Relocatable Facilities Manager
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.01c | |
Hillsborough County Public Schools (Florida) * Mtg.#20080904_299 * Section A Item# 6.01c |