Approve Construction Documents and Guaranteed Maximum Price for Interior Build Out at
North Tampa Alternative School

EXECUTIVE SUMMARY

Long & Associates Architects/Engineers, Inc. and Halfacre Construction Company were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provides for the interior build out of office spaces at North Tampa Alternative School. Project completion is scheduled for October 5, 2008.

Approval of the guaranteed maximum price will establish a cost for the project.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $34,635.90. The construction budget is $34,650.00. This item is included in the District Capital Outlay: Millage Funds.

EVALUATION

SUBMITTED BY: Ken Tomberlin, Relocatable Facilities Manager

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004