Hillsborough County Public Schools Facilities
Action Item

DATE: Thursday, November 6, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 11 in the Amount of $109,300.00 Extra for
Rampello Downtown Partnership School, New Facility

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Alfonso Architects, Inc. On March 12, 2002, the Board appointed the construction management firm of J.O. DeLotto & Sons, Inc. The scope of work included construction of a new K-8 school to house 1,226 students.

This change order provides for a handicap ramp, tree grates, pavement striping, and other site modifications as required by the City of Tampa.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2003.

Contract Status:
Guaranteed Maximum Price: $11,277,514.00
Change Orders Previously Approved: $1,743,717.74 Credit
Change Order Recommended Herein: $109,300.00 Extra
Revised Guaranteed Maximum Price: $9,643,096.26
Revised Construction Cost: $12,189,489.04

Original Completion Date: May 6, 2005
Time Extension Previously Approved: 21 Calendar Days
Revised Completion Date: May 27, 2005

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.16
Hillsborough County Public Schools (Florida) * Mtg.#20081106_303 * Section A Item# 6.16