Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, December 9, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Classrooms for Kids Addition at
Marshall Middle School (Painting)

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed John J. McKenna Architect P.A. and W.G. Mills, Inc. to provide design and construction management services for the classroom addition. On July 29, 2008, the Board approved the amendment of existing agreements to include interior painting throughout the facility and painting of exterior trim and canopies.

The architect advises that the painting project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.

Contract Status:
Guaranteed Maximum Price: $349,839.00
Change Order Previously Approved: $10,742.53 Credit
Revised Guaranteed Maximum Price: $339,096.47
Payments to Date: $338,096.47
Balance Due: $1,000.00
Revised Construction Cost: $337,937.92

Contract Completion Date: August 8, 2008
Substantial Completion Date: August 8, 2008

EVALUATION

SUBMITTED BY: Eugene Runnels, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.30
Hillsborough County Public Schools (Florida) * Mtg.#20081209_314 * Section A Item# 6.30