Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, December 9, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 2 in the Credit Amount of $164,157.74 for Classroom Addition at
Bryant Elementary School

EXECUTIVE SUMMARY

On July 11, 2006, the Board appointed the architectural firm of Schenkel Shultz Architecture with Batson-Cook Company providing construction management services. The scope of work provides for the addition of 16 primary classrooms.

This change order provides a credit for project savings and the return of unused contingency funds.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax 02 and 06.

Contract Status:
Guaranteed Maximum Price: $2,948,367.00
Change Order Previously Approved: $508,803.92 Credit
Change Order Recommended Herein: $164,157.74 Credit
Revised Guaranteed Maximum Price: $2,275,405.34
Revised Construction Cost: $2,754,433.26

Contract Completion Date: April 3, 2008

EVALUATION

SUBMITTED BY: Ellis Curry, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004