Approve Change Order No. 6 in the Credit Amount of $497,322.39 and a Time Extension of 1 Calendar Day for Renovation at
Knights Elementary School

EXECUTIVE SUMMARY

On July 11, 2006, the Board appointed Reynolds, Smith & Hills, Inc. and Mathews Construction to provide design and construction management services. The renovation of existing facilities provides for a new walkway canopy and fire sprinkler system; reconfiguration of driveways and visitor parking; interior and exterior painting; and replacement of roof, plumbing fixtures, exterior doors, low voltage systems, and heating, ventilating, and air conditioning (HVAC) equipment.

This change order provides a credit for project savings and the return of unused contingency funds. A time extension of one calendar day is included to accommodate completion of additional needed renovations requested by the District.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Capital Outlay and Debt Service (CO and DS) 06A ($3,000,000) and Community Investment Tax (CIT) 06 ($450,000).

Contract Status:
Guaranteed Maximum Price: $3,450,000.00
Change Orders Previously Approved: $497,052.72 Credit
Change Order Recommended Herein: $497,322.39 Credit
Revised Guaranteed Maximum Price: $2,455,624.89
Revised Construction Cost: $2,987,819.28

Original Completion Date: July 14, 2008
Time Extension Recommended Herein: 1 Calendar Day
Revised Completion Date: July 15, 2008

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.21