Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, December 9, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 1 in the Credit Amount of $32,680.16 and Acceptance of Project for HVAC Renovation at
Lanier Elementary School and Tomlin Middle School

EXECUTIVE SUMMARY

Consulting Engineering Associates, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 20, 2008, the Board awarded the contract for construction to the low bidder, Serge's Air Conditioning & Heating, Inc. The scope of work provided for modification of the heating, ventilating, and air conditioning (HVAC) system in Building 100 at Lanier Elementary School and Buildings 600 and 700 at Tomlin Middle School.

This change order provides for final reconciliation of the Direct Purchase Program.

The engineer advises that the project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

These items were included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.

Contract Status:
Contract Sum: $177,202.00
Change Order Recommended Herein: $32,680.16 Credit
Revised Contract Sum: $144,521.84
Payments to Date: $130,069.66
Balance Due: $14,452.18
Revised Construction Cost: $175,257.84

Contract Completion Date: August 18, 2008
Substantial Completion Date: August 8, 2008

EVALUATION

SUBMITTED BY: Ernie MacFerran, Mechanical Engineer

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.25
Hillsborough County Public Schools (Florida) * Mtg.#20081209_314 * Section A Item# 6.25