Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, January 27, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 3 in the Amount of $1,785.49 Extra for Classrooms for Kids Addition at
Lutz Elementary School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed Harvard Jolly, Inc. and Greater Bay Construction Co., Inc. to provide design and construction management services. The scope of work provides for an additional 12 classrooms. This addition was necessary to meet class size reduction requirements.

This change order provides for final reconciliation of the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $2,077,794.00
Change Orders Previously Approved: $368,037.12 Credit
Change Order Recommended Herein: $1,785.49 Extra
Revised Guaranteed Maximum Price: $1,711,542.37
Revised Construction Cost: $2,056,263.61

Contract Completion Date: August 4, 2008

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.17
Hillsborough County Public Schools (Florida) * Mtg.#20090127_342 * Section A Item# 6.17