Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, January 27, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 3 in the Amount of $24,021.92 Extra for
Kimbell Elementary School, New Facility

EXECUTIVE SUMMARY

On December 18, 2007, the Board appointed The Architectural Practice, Inc. and Batson-Cook Company to provide design and construction management services. Based on the approved boundaries, this school relieved Forest Hills and Pizzo Elementary Schools.

This change order provides for final reconciliation of the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Classrooms for Kids 2007-08.

Contract Status:
Guaranteed Maximum Price: $12,367,258.00
Change Orders Previously Approved: $2,520,021.97 Credit
Change Order Recommended Herein: $24,021.92 Extra
Revised Guaranteed Maximum Price: $9,871,257.95
Revised Construction Cost: $12,224,418.40

Contract Completion Date: August 1, 2008

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004