Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, January 27, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Schematic Design and Design Development Phases for HVAC Renovation at
Brewster Technical Center

EXECUTIVE SUMMARY

On July 15, 2008 the Board appointed the firm of KPI Engineering Inc. to provide design services. The scope of work provides for renovation of the heating, ventilating, and air conditioning (HVAC) system.

Approval of the schematic design and design development phases will allow the engineer to proceed with construction documents. Project completion is scheduled for February 2010.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

Construction budget is $2,115,080. The estimate of probable cost is $2,111,425. This item is included in the Public Education Capital Outlay (PECO) Maintenance.

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.08
Hillsborough County Public Schools (Florida) * Mtg.#20090127_342 * Section A Item# 6.08