Facilities Action Item |
DATE: Tuesday, February 10, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On February 13, 2007, the Board appointed Rodriguez + Architecture / AIA / PA and Christiano Construction Company, Inc. to provide design and construction management services. The renovation of existing facilities includes replacement or refurbishment of interior finishes and hardware; power, lighting, and low-voltage system upgrades; mechanical and drainage system repairs, and exterior repairs; waterproofing and painting. The administration building will be remodeled and reconfigured.
This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction 06-07.
Contract Status:
Guaranteed Maximum Price: $3,070,000.00
Change Order Previously Approved: $465,778.72 Credit
Change Order Recommended Herein: $78,220.01 Credit
Revised Guaranteed Maximum Price: $2,526,001.27
Revised Construction Cost: $3,038,830.25
Contract Completion Date: April 8, 2009
EVALUATION
SUBMITTED BY: John Williams, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.07 | |
Hillsborough County Public Schools (Florida) * Mtg.#20090210_343 * Section A Item# 6.07 |