Facilities Action Item |
DATE: Tuesday, February 24, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On February 19, 2008, the Board appointed Rowe Architects, Inc. and Batson-Cook Company to provide design and construction management services. The renovation of existing facilities provides for locker refinishing; interior painting; door hardware, toilet accessories, and other miscellaneous handicap accessibility upgrades; roof refurbishment; replacement of acoustical ceilings; replacement of worn carpet with vinyl composition tile (VCT); and heating, ventilating, and air conditioning (HVAC) and fire sprinkler system replacements. Project completion is scheduled for August 12, 2010.
Approval of the guaranteed maximum price will establish a cost for the project.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction cost is warranted at $9,307,820. The construction budget is $9,324,688. This item is included in the District Capital Outlay: Local Millage.
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.04b | |