Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, February 24, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Construction Documents and Guaranteed Maximum Price for Restoration of Fire Damaged Bathroom at
Freedom High School

EXECUTIVE SUMMARY

Greater Bay Construction Company, Inc. was selected from the approved Continuing Services Consultants list to provide construction management services. The scope of work provides for restoration of a fire damaged bathroom to the original specifications. Project completion is scheduled for March 25, 2009.

Approval of the guaranteed maximum price will establish a cost for the project.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $89,083. The construction budget is $89,100. This item is included in the District Capital Outlay: Local Millage.

EVALUATION

SUBMITTED BY: Clay Ward, Manager Facilities Maintenance Support

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.04c
Hillsborough County Public Schools (Florida) * Mtg.#20090224_344 * Section A Item# 6.04c