Approve Change Order No. 7 in the Credit Amount of $559,251.09 for
Steinbrenner High School, New Facility

EXECUTIVE SUMMARY

On July 26, 2005, the Board appointed HCBeck, Ltd. to provide construction management services. This new facility is a reuse of the Middleton High School design. As of the current boundaries, relief will be provided for Alonso, Gaither, and Sickles High Schools.

This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2004C ($8,054,496) and 2006 ($39,035,771).

Contract Status:
Guaranteed Maximum Price: $47,090,267.00
Change Orders Previously Approved: $12,662,781.58 Credit
Change Order Recommended Herein: $559,251.09 Credit
Revised Guaranteed Maximum Price: $33,868,234.33
Revised Construction Cost: $45,394,916.06

Contract Completion Date: July 30, 2009

EVALUATION

SUBMITTED BY: John Williams, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer