Facilities Action Item |
DATE: Tuesday, April 21, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On May 20, 2008, the Board appointed Long & Associates Architects/Engineers, Inc. and Halfacre Construction Company to provide design and construction management services for relocatable and modular facilities. The scope of work at Gary Adult High School provides for installation of a modular facility to serve as a Life Skills Learning Center.
This change order provides a credit for project savings and the return of unused contingency funds.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Ken Tomberlin, Relocatable Facilities Manager
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.11 | |
Hillsborough County Public Schools (Florida) * Mtg.#20090421_348 * Section A Item# 6.11 |