EXECUTIVE SUMMARY
John J. McKenna Architect P.A. was selected from the approved Continuing Services Consultants list to provide design services. On May 20, 2008, the Board awarded the contract for construction to the low bidder, All Area Roofing and Waterproofing, Inc. The scope of work provides for replacement of the roof at West Tampa Elementary School.
This change order provides for removal of unforeseen insulation discovered in the process of replacing the roof.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Ellis Curry, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |