Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 19, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 1 in the Amount of $682.30 Credit, and Change Order No. 2 for a 68 Calendar Day Time Extension, and Acceptance of Project for Exterior Weatherproofing and Painting at
Walden Lake Elementary School

EXECUTIVE SUMMARY

Weber and Tinnen, P.A., and Walbridge, Inc., were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provided for weatherproofing and painting of selected exterior walls and all exterior metal surfaces at Walden Lake Elementary School.

Change Order No. 1 provides a credit for unused contingency funds. Change Order No. 2 provides a 68 calendar day time extension for weather delays.

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction 07-08

Contract Status:
Contract Sum: $325,814.00
Change Order No. 1 Recommended Herein: $682.30 Credit
Revised Contract Sum: $325,131.70
Payments to Date: $325,131.70
Balance Due: $-0-
Contract Completion Date: September 15, 2008
68 Calendar Day Time Extension: Recommended Herein
Revised Completion Date: November 21, 2008
Substantial Completion Date: November 21, 2008

EVALUATION

SUBMITTED BY:

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.13
Hillsborough County Public Schools (Florida) * Mtg.#20090519_351 * Section A Item# 6.13