Facilities Action Item |
DATE: Tuesday, June 9, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
Kisinger Campo & Associates Corp. was selected from the approved Continuing Services Consultants list to provide design services. The scope of work provides for the addition of 95 paved parking spaces at Sulphur Springs Elementary School. On January 27, 2009, the Board awarded the contract for construction to the low bidder, Newco Construction Company (doing business as Wichman Construction).
This change order provides a credit of five days of liquidated damages at $300 per day resulting from the late substantial completion. A time extension of two calendar days is included for rain delays.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Jill Edwards, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.24 | |
Hillsborough County Public Schools (Florida) * Mtg.#20090609_352 * Section A Item# 6.24 |