Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, July 14, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 1 in the Credit Amount of $1,225,973.77 for Renovation at
Burns Middle School

EXECUTIVE SUMMARY

On February 19, 2008, the Board appointed Rowe Architects, Inc. and Batson-Cook Company to provide design and construction management services. The renovation of existing facilities provides for locker refinishing; interior painting; door hardware, toilet accessories, and other miscellaneous handicap accessibility upgrades; roof refurbishment; replacement of acoustical ceilings; replacement of worn carpet with vinyl composition tile (VCT); and heating, ventilating, and air conditioning (HVAC) and fire sprinkler system replacements.

This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Local Millage.

Contract Status:
Guaranteed Maximum Price: $9,307,820.00
Change Order Recommended Herein: $1,225,973.77 Credit
Revised Guaranteed Maximum Price: $8,081,846.23
Revised Construction Cost: $9,237,859.23

Contract Completion Date: August 12, 2010

EVALUATION

SUBMITTED BY: Eugene Runnels, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.12
Hillsborough County Public Schools (Florida) * Mtg.#20090714_356 * Section A Item# 6.12