Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, September 15, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 10 in the Amount of $117,589.39 Extra for
Steinbrenner High School, New Facility

EXECUTIVE SUMMARY

On July 26, 2005, the Board appointed HCBeck, Ltd. to provide construction management services. This new facility, which opened in August 2009, was a reuse of the Middleton High School design and relieved overcrowding at Alonso, Gaither, and Sickles High Schools.

This change order provides an adjustment to the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2004C ($8,054,496) and 2006 ($39,035,771).

Contract Status:
Guaranteed Maximum Price: $47,090,267.00
Change Orders Previously Approved: $13,352,268.67 Credit
Change Order Recommended Herein: $117,589.39 Extra
Revised Guaranteed Maximum Price: $33,855,587.72
Revised Construction Cost: $45,393,526.34

Contract Completion Date: July 30, 2009

EVALUATION

SUBMITTED BY: John Williams, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.10
Hillsborough County Public Schools (Florida) * Mtg.#20090915_361 * Section A Item# 6.10