Facilities Action Item |
DATE: Tuesday, September 15, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On March 8, 2005, the Board appointed Gould Evans Associates and Manhattan Construction Company to provide design and construction management services. The scope of work includes the demolition and replacement of the Administration, Media, and classroom buildings.
This change order provides a credit for the return of unused contingency funds. A time extension of 34 calendar days and costs for increased general conditions items associated with the time extension are included for installation of anti-terrorism windows as requested by MacDill Air Force Base.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Community Investment Tax ($6,287,933) and Capital Outlay and Debt Service ($1,232,260).
Contract Status:
Guaranteed Maximum Price: $7,520,193.00
Change Orders Previously Approved: $892,718.20 Credit
Change Order Recommended Herein: $45,910.79 Credit and $39,106.00 Extra
Revised Guaranteed Maximum Price: $6,620,670.01
Revised Construction Cost: $7,885,402.33
Original Completion Date: February 19, 2008
Time Extension Previously Approved: 161 Calendar Days
Time Extension Recommended Herein: 34 Calendar Days
Revised Completion Date: September 1, 2008
EVALUATION
SUBMITTED BY: Ellis Curry, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |