Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, October 6, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 1 in the Credit Amount of $19,479.80 and Change Order No. 2 in the Amount of $3,065.90 Extra for Roof Replacement at
Mann Middle School

EXECUTIVE SUMMARY

Reliable Group Architects was selected from the approved Continuing Services Consultants list to provide design services. On April 21, 2009, the Board awarded the contract for construction to Anderson & Shah Roofing, Inc. to provide construction management services. The scope of work provides for roof, edge metal, and roof drain replacement on selected buildings.

Change Order No. 1 provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program. Change Order No. 2 provides for revisions to the storm gutter installation details and relocation of an air conditioning unit, required due to unforeseen conditions.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Local Millage.

Contract Status:
Contract Sum: $60,000.00
Change Order No. 1 Recommended Herein: $19,479.80 Credit
Change Order No. 2 Recommended Herein: $3,065.90 Extra
Revised Contract Sum: $43,586.10
Revised Construction Cost: $61,916.10

Contract Completion Date: July 12, 2009

EVALUATION

SUBMITTED BY: Hung Pham, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.15
Hillsborough County Public Schools (Florida) * Mtg.#20091006_362 * Section A Item# 6.15