This design-build project was planned by the Facilities Division. The scope of work provides for a metal playcourt canopy at Citrus Park Elementary School. An interlocal agreement with Hillsborough County Parks, Recreation, and Conservation Department, approved by the Board on May 5, 2009, provides for funding from the County in the amount of $157,976. On May 5, 2009, the Board awarded the contract for construction to Caladesi Construction Company.
Change Order No. 1 provides for final reconciliation of the Direct Purchase Program. Change Order No. 2 provides for installation of an additional canvas canopy as requested by school administration. A time extension is included for completion of the work.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Expenditures are funded as follows: $157,976 from Hillsborough County and $25,000 from the school's contribution (any unused funds will be returned to the school). Therefore, there is no financial impact to the District.
Contract Status:
Contract Sum: $163,694.00
Change Order No. 1 Recommended Herein: $48,231.24 Credit
Change Order No. 2 Recommended Herein: $5,600.00 Extra
Revised Contract Sum: $121,062.76
Revised Construction Cost: $166,516.76
Original Completion Date: September 18, 2009
Time Extension Recommended in Change Order No. 2: 15 Calendar Days
Revised Completion Date: October 3, 2009
EVALUATION
SUBMITTED BY: Hung Pham, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.12 | |
Hillsborough County Public Schools (Florida) * Mtg.#20091020_363 * Section A Item# 6.12 |