EXECUTIVE SUMMARY
On May 20, 2008, the Board appointed the architectural firm of Carruthers & Associates Architects P.A. to provide design services. On July 15, 2008, the Board appointed the construction management firm of Vogel Bros. Building Co. The scope of work provides for an additional 8 classrooms. This addition is necessary to meet class size reduction requirements.
Change Order No. 5 provides a credit for project savings. Change Order No. 6 provides for final reconciliation of the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Jill Edwards, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |