Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, November 17, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 1 in the Credit Amount of $110,564.49 and Change Order No. 2 for a 22 Calendar Day Time Extension for Roof Replacement at
Van Buren Middle School

EXECUTIVE SUMMARY

Reliable Group Architects was selected from the approved Continuing Services Consultants list to provide design services. On April 21, 2009, the Board awarded the contract for construction to Quality Roofing of Florida, Inc. The scope of work provides for roof, edge metal, and roof drain replacement on selected buildings.

Change Order No. 1 provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program. Change Order No. 2 provides a 22 calendar day time extension for rain delays and removal of unforeseen structural concrete.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.

Contract Status:
Contract Sum: $260,100.00
Change Order No. 1 Recommended Herein: $110,564.49 Credit
Change Order No. 2 Recommended Herein: $0.00 Extra
Revised Contract Sum: $149,535.51
Revised Construction Cost: $253,794.46

Original Completion Date: August 2, 2009
Time Extension Recommended in Change Order No. 2: 22 Calendar Days
Revised Completion Date: August 24, 2009

EVALUATION

SUBMITTED BY: Hung Pham, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.14
Hillsborough County Public Schools (Florida) * Mtg.#20091117_366 * Section A Item# 6.14