Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, January 12, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 3 for a Time Extension of 52 Calendar Days for Roof Replacement at
Mann Middle School

EXECUTIVE SUMMARY

Reliable Group Architects was selected from the approved Continuing Services Consultants list to provide design services. On April 21, 2009, the Board awarded the contract for construction to Anderson & Shah Roofing, Inc. The scope of work provides for roof, edge metal, and roof drain replacement on selected buildings.

This change order provides for a time extension of 52 calendar days for rain delays and approval of the proposed roofing system by the District's Building Code Office.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Local Millage.

Contract Status:
Contract Sum: $60,000.00
Change Orders Previously Approved: $16,413.90 Credit
Revised Contract Sum: $43,586.10
Revised Construction Cost: $61,916.10

Original Completion Date: July 12, 2009
Time Extension Recommended Herein: 52 Calendar Days
Revised Completion Date: September 2, 2009

EVALUATION

SUBMITTED BY: Hung Pham, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.03
Hillsborough County Public Schools (Florida) * Mtg.#20100112_390 * Section A Item# 6.03