SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for HVAC Replacement and Refinishing at
Sligh Middle School

EXECUTIVE SUMMARY

On March 8, 2005, the Board appointed the architectural firm of Ruyle Hayes + Jennewein Architects P.A. to provide design services for a new gymnasium. The design scope was subsequently expanded to include replacement of the heating, ventilating, and air conditioning (HVAC) system, interior repainting, and replacement of floor finishes in the existing school. On February 27, 2007, the Board awarded the contract for construction to Air Mechanical & Service Corp.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Local Millage.

Contract Status:
Contract Sum: $2,894,000.00
Change Orders Previously Approved: $108,592.20 Credit
Revised Contract Sum: $2,785,407.80
Payments to Date: $2,764,585.80
Balance Due: $20,822.00
Revised Construction Cost: $2,925,707.80

Original Completion Date: December 24, 2007
Time Extension Previously Approved: 63 Calendar Days
Revised Completion Date: February 25, 2008
Substantial Completion Date: May 15, 2008

EVALUATION

SUBMITTED BY: James Lipsey, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004